Explain the types of tube failure that may occur innthe initial stage of boiler operation till stabilization?
During the initial stage of boiler operation, until the system reaches a stable operational phase, several types of tube failures can occur. These failures are often related to start-up conditions, improper handling, design flaws, or material weaknesses. The initial period of boiler operation is critical, as it involves high thermalRead More
High Pressure Bypass Fast open Condition
Turbine trip GCB open LSR operated Emergency fast open push button pressed Pressure deviation high ( actual pressure- HPBP pressure setpoint => 8ksc)
FSSS (Furnace Safeguard Supervisory System)
FSSS LOGIC SYSTEM BOILER START- UP SEQUENCE The boiler can be placed in service, initially or after a “Master Fuel Trip,” in the following sequence through FSSS. Furnace Purge:- Before any fuel firing can takes place, initially or following a boiler trip, a satisfactory “Purge Cycle” must be completed. Initially,Read More
MAHARASHTRA STATE BOILER OPERATION ENGINEERING EXAM 2013